AIA B101-Style Standard Form of Architect Agreement & 5-Phase Design Fee Schedule
Standard / Reference: AIA Document B101 Standard · NCARB Rules of Conduct · 17 U.S.C. § 120 Architectural Works
Why professionals use this template: 14,200/mo search demand: architectural firms requiring structured 5-phase fee billing (SD 15%, DD 20%, CD 40%, Bidding 5%, CA 20%) and Instruments of Service copyright protection.
144-DPI VECTOR PREVIEW · PAGE 1 OF 1
ACROFORM READY
Included Financial Metrics & Line-Item Schedule
Target Roles: Licensed Architects (AIA), Commercial Developers & Design-Build Principals · Search Keywords: aia b101 architect agreement and phased design fee schedule template pdf, architectural basic services 5 phase fee breakdown, instruments of service copyright license, schematic design to construction admin invoice
CONSTRUCTION BUDGET BASIS
$2,850,000.00
ARCHITECT BASIC FEE (6.5%)
$185,250.00 TOTAL
PHASES BILLED TO DATE
SD + DD (35% Complete)
CURRENT PHASE DRAW DUE
$37,050.00 (DD FREEZE)
| CODE | DESCRIPTION & TECHNICAL SPECIFICATION | BASIS / QTY | AMOUNT / DELTA |
|---|---|---|---|
| PH-01-SD | Phase 1 — Schematic Design (15%): Site Massing, Code Analysis & Conceptual Floor Plans | 100% Complete | $27,787.50 |
| PH-02-DD | Phase 2 — Design Development (20%): Structural Grid, MEP Coordination & Exterior Elevations | 100% Complete | $37,050.00 |
| PH-03-CD | Phase 3 — Construction Documents (40%): Stamped Permit Drawings & CSI MasterFormat Specs | In Progress (60%) | $74,100.00 |
| PH-04-CA | Phases 4 & 5 — Bid Negotiation (5%) & Construction Administration Submittal/RFI Review (20%) | Upcoming Phase | $46,312.50 |
Related Inspection, Appraisal & Clean Energy Templates
- #41 — Residential Home Inspection Defect Summary & Buyer Repair Request Addendum (ASHI / InterNACHI Standards of Practice · Buyer Inspection Contingency Resolution)
- #42 — Solar PV + LFP Battery Storage Engineering Proposal & 25-Year Cash-Flow Schedule (NEC Article 690 / 706 · NREL PVWatts® v8 Production Model · IRC § 25D / § 48E Credit)
- #43 — USPAP Restricted Real Estate Appraisal & Sales Comparison Adjustment Grid (2024–2026 USPAP Standards Rule 2-2(b) · Mandatory SR 2-3 Appraiser Certification)
- #44 — Phase I Environmental Site Assessment (ASTM E1527-21) Executive REC Summary (ASTM E1527-21 Standard · 40 C.F.R. Part 312 (CERCLA Innocent Landowner AAI Defense))
- #45 — ALTA/NSPS Land Title Boundary Survey Certification, Zoning & Table A Schedule (2021 ALTA/NSPS Minimum Standard Detail Requirements · Relative Positional Precision < 0.07 ft)
- #57 — Geotechnical Engineering Subsurface Soil Boring Log & Foundation Bearing Report (ASTM D1586 (SPT Blow Counts) · ASTM D2487 (USCS Soil Class) · 2021 IBC Chapter 18 § 1803)
- #58 — Civil Engineering Stormwater Hydrology, TR-55 Runoff & Detention Basin SWPPP Study (Clean Water Act § 402 NPDES · USDA NRCS TR-55 Method · Municipal MS4 Stormwater Ordinance)
- #59 — Utility-Scale Commercial Solar Interconnection Application & Stamped 3-Line Diagram Packet (IEEE 1547-2018 Standard · UL 1741-SB Smart Inverter Cert · NEC Article 705 Interconnected Systems)
- #60 — IBC Chapter 17 Structural Special Inspection, Concrete Cylinder & CWI Weld Affidavit (2021 IBC Chapter 17 § 1704 · ASTM C39 Concrete Compression · AWS D1.1 Structural Welding Code)