Construction Change Order & Schedule Impact Directive

Standard / Reference: AIA G701 Standard · Statutory Written Change Directive · OH&P Markup Disclosure

Why professionals use this template: r/Contractors & r/sweatystartup top pain point: preventing unpaid scope creep by requiring signed cost + calendar day impact approval before work.

Customize Layout & Elements Live

Download Fillable PDF ↗
144-DPI VECTOR PREVIEW · PAGE 1 OF 1 ACROFORM READY
Construction Change Order & Schedule Impact Directive preview

Included Financial Metrics & Line-Item Schedule

Target Roles: Remodelers, Custom Home Builders & Trade Subcontractors · Search Keywords: construction change order template pdf with schedule impact, contractor scope change form, signed change order form, time and materials markup sheet

PRIOR CONTRACT TOTAL
$142,500.00
NET CHANGE ORDER #03
+$14,820.00
SCHEDULE EXTENSION
+6 Working Days
NEW REVISED CONTRACT SUM
$157,320.00
CODE DESCRIPTION & TECHNICAL SPECIFICATION BASIS / QTY AMOUNT / DELTA
CO-03.1Engineered LVL Flush Beam Upgrade (2x 1.75" x 14" Microllam + Steel Flitch)24 LF Installed$5,840.00
CO-03.2Relocate 200A Sub-Panel & 4 Home-Run AFCI Circuits in Load-Bearing Wall16 Hrs Master Elec$3,920.00
CO-03.3Custom White Oak Waterfall Island Countertop & Concealed Steel Brackets42 Sq Ft Fab$3,600.00
CO-03.4General Conditions, Permit Amendment & 10% Overhead / 10% ProfitStatutory OH&P$1,460.00